We stick with the theory of "quality first, company first, steady improvement and innovation to satisfy the customers" for the management and "zero defect, zero complaints" as the quality objective. To perfect our provider, we deliver the items together with the fantastic good quality at the reasonable value for Fresh Air Control, Sterilization And Sterilization, Power Distribution For Lighting Equipment,Air Filter,Air Conditioner Filter Cleaning,, Our professional technical team will be wholeheartedly at your service. We sincerely welcome you to visit our website and company and send us your inquiry.
Newly Arrival Hot Water Distribution - Process pipeline installation – TekMax Detail:

①. Installation preparation: Be familiar with the drawings carefully, and make preparations according to the construction method determined by the construction plan and the specific measures of technical disclosure. Refer to relevant professional equipment drawings and decoration building drawings, check whether the coordinates and elevations of various pipelines are crossed, whether the space used for pipeline arrangement is reasonable, and if there is a problem, study and solve the problem with the relevant personnel of the design unit in time, and make a change and negotiation record.

Prefabrication processing: according to the design drawings, draw the construction sketches of the pipeline branch, pipe diameter, reduced diameter, reserved nozzle, valve position, etc., in the actual installation structure position

② Make a mark, measure the exact size of the actual installation according to the marked section, and record it on the construction sketch; then, check whether the pipes and accessories are supplied by the manufacturer, and after confirming that they are correct, prefabricate according to the measured size of the sketch (Broken pipes, fittings, proofreading, group numbers by pipe sections, etc.).

③, dry pipe installation

The riser shall be hoisted from top to bottom to install the clamps, and the height of the clamps near the shear wall shall be 1.8 meters, or a steel composite bracket shall be installed at the pipe well head, and the prefabricated risers shall be installed in a hierarchical order according to the number. Straighten. Temporary plugs should be installed at the branch pipes. The installation direction of the riser valve should be convenient for operation and repair. After installation, use a wire pendant to straighten it, fix it with clamps, and plug the floor hole in cooperation with the civil construction. The installation of multiple risers in the tube well should be installed in the order of the inside first and then the outside, first big and then small. The mark of domestic water pipe is light green, fire pipe is red, rain water pipe is white, and domestic sewage pipe is white.

④ Branch pipe installation

For concealed application of branch pipes in toilets, the length of branch pipes should be determined and then drawn and positioned. Light-weight walls are slotted with a slotting machine, and the prefabricated branch pipes are laid in the grooves. After leveling and alignment, use hook nails or steel nails to bind galvanized iron wires to fix the pipe ; The valve and detachable parts should be provided with inspection holes; each water distribution point should be installed with a bulkhead pipe with a length of 100mm or 150mm, and be aligned and leveled, and then perform a pressure test on the concealed pipeline. After the test is accepted, the pipe groove shall be covered with cement mortar in time.

⑤, pipeline pressure test

The concealed and insulated water supply pipes should be tested individually before being concealed, and the system should be tested after the installation of the piping system. In the hydraulic test, the internal air must be drained first, and then the water should be filled into the water pipe. The pressure is slowly increased to the specified requirement for 6 hours. There is no leakage in the first 2 hours. After 6 hours, the pressure drop does not exceed 5% of the test pressure to be qualified. The general contractor, the supervisor and the relevant personnel of Party A can be notified of the acceptance, go through the visa procedures, and then drain the water, and fill in the pipeline pressure test record in time.


Product detail pictures:

Newly Arrival  Hot Water Distribution - Process pipeline installation – TekMax detail pictures


Related Product Guide:

We believe in: Innovation is our soul and spirit. Quality is our life. Customer need is our God for Newly Arrival Hot Water Distribution - Process pipeline installation – TekMax , The product will supply to all over the world, such as: Mali, Islamabad, Madrid, For more than ten years experience in this filed, our company has gained high reputation from home and abroad. So we welcome friends from all over the world to come and contact us, not only for business, but also for friendship.
  • The manufacturer gave us a big discount under the premise of ensuring the quality of products, thank you very much, we will select this company again.
    5 Stars By Christina from Guatemala - 2017.06.29 18:55
    Managers are visionary, they have the idea of "mutual benefits, continuous improvement and innovation", we have a pleasant conversation and Cooperation.
    5 Stars By Christopher Mabey from Moscow - 2018.09.21 11:44
    Write your message here and send it to us